The installation of a fully automatic high-speed printing slotting die-cutting machine is a complex and delicate process involving multiple steps and key points.

2025-10-24
 Latest company case about The installation of a fully automatic high-speed printing slotting die-cutting machine is a complex and delicate process involving multiple steps and key points.

The installation of a fully automatic high-speed printing slotting die-cutting machine is a complex and delicate process involving multiple steps and key points.

 

The following is a general overview of its installation process:

 

1. Preliminary preparation

 

Site planning:

According to the equipment size and layout requirements, rationally plan the installation site toensure that the equipment has enough space for installation and operation.

 

The site should be flat and solid, and able to withstand the weight of the equipment and vibrationduring operation.

 

Foundation construction:

According to the equipment requirements, construct the equipment foundation to ensure that the size, elevation, levelness, etc. of the foundation meet the design requirements.

 

After the foundation construction is completed, an acceptance inspection is carried out to ensure that the equipment can be installed only after it is qualified.

 

Equipment inspection:

Before installation, conduct a comprehensive inspection of the equipment, including appearance, component integrity, random data, etc., to ensure that the equipment is not damaged or missing.

 

2. Installation steps

 

Host installation:

Lift the host to the predetermined position, adjust the level, and ensure that the equipment is stable and does not shake.

 

According to the equipment manual, connect the transmission mechanism, electrical circuit, etc. between the components.

 

Paper feed unit installation:

Install the paper feed unit, including the paper feed wheel, suction device, etc., to ensure smoothand accurate paper feeding.

 

Debug the paper feeding unit, adjust the paper feeding speed and paper feeding accuracy to meet the printing requirements.

 

Installation of the printing unit:

Install the printing roller, anilox roller and other printing components to ensure that they are installed in place and operate flexibly.

 

Connect the ink supply system, debug the ink supply and printing effect, and ensure the printing quality.

 

Installation of the slotting and die-cutting unit:

Install the slotting knife, die-cutting knife and other components to ensure cutting accuracy and stability.

 

Debug the slotting and die-cutting unit, adjust the cutting depth and speed to meet product requirements.

 

Installation of the electrical control system:

According to the electrical schematic diagram, connect the electrical components and lines toensure the normal operation of the control system.

Debug the control system, including the touch screen, PLC, etc., to ensure that all functions are normal.

 

Installation of the lubrication system:

Install the lubrication system, including oil pumps, oil pipes and other components, to ensure that all lubrication points of the equipment are fully lubricated.

Debug the lubrication system and set a reasonable lubrication cycle and oil volume.

 

Installation of safety devices:

Install necessary safety devices, such as protective covers, emergency stop buttons, etc., to ensure the safe operation of the equipment.

 

3. Debugging and acceptance

 

No-load test run:

Under no-load condition, start the equipment for no-load test run to check whether the operationof each component is normal.

Adjust equipment parameters to optimize equipment performance.

 

Load test run:

When the rated load is reached, load test run is carried out to check whether the equipment's carrying capacity, printing quality, cutting accuracy, etc. meet the requirements.

 

Acceptance:

According to the equipment technical specifications and acceptance standards, the equipment is fully accepted. Only after acceptance can it be put into formal production and use.

 

4. Precautions Professional installation:

 

The installation of the fully automatic high-speed printing slotting die-cutting machine should be carried out by professionals to ensure the quality and safety of the installation.

 

Follow the instructions:

During the installation process, the installation steps and requirements in the equipment manual should be strictly followed.

 

Safety first:

During the installation process, safety should always be paid attention to, and relevant safetyregulations and operating specifications should be followed.

 

Record and archive:

The key steps and debugging results in the installation process are recorded and archived for subsequent reference and maintenance.

By following the above steps and precautions, the installation of the fully automatic high-speedprinting slotting die-cutting machine can be ensured to proceed smoothly and achieve the expectedresults.